top of page
Writer's pictureBusainganon_1982

Construction of Slope Protection - Peñafrancia

PROJECT COST:    125,000.00

IMPLEMENTATION MODE: BY ADMINISTRATION

SUPPLIER: A. GALLANOSA HARDWARE

UTILIZATION: 120,174.00

A.     Materials & Supply:    91, 154.00

B.      Labor & Payroll:           29, 020.00

                                                120,174.00

 

STATUS: COMPLETED

PROJECT DURATION: JAN 4-17, 2023

PROJECT DURATION




12 views0 comments

Yorumlar

5 üzerinden 0 yıldız
Henüz hiç puanlama yok

Puanlama ekleyin
bottom of page