Construction of Pathway - San Isidro

PROJECT COST:    125,000.00

IMPLEMENTATION MODE: BY ADMINISTRATION 

SUPPLIER:  A. GALLANOSA HARDWARE

UTILIZATION:

A.     Materials & Supply:    88, 025.50

B.      Labor & Payroll:          29,  710.00

                                               118, 735.5

STATUS: COMPLETED

PROJECT DURATION : January 9-26, 2023






30 views0 comments